BP Top kill procedure - aptly named?


Top kill procedure diagram (jpg, 729KB)

The primary objective of the top kill process is to put heavy kill mud into the well so that it reduces the pressure and then the flow from the well. Once the kill mud is in the well and it’s shut down, then we follow up with cement to plug the leak.

For the top kill procedure we are designing equipment to pump the highest kill rate we can, irrespective of the flow rate of oil from the well (COMMENT: Wouldn't having an accurate estimate of the output of the well allow you to make better decisions regarding the practicality of this approach?), to force a downward flow of mud into the well. This, combined with the heavy drilling fluid is designed to eventually stop the flow. This has never been attempted at these depths. This is very complex – and involves several complex procedures coming together.

Detailed description of the procedure We have the Q4000 vessel at the surface which has a crane for lifting heavy equipment and is a central part of the surface equipment for this procedure. We also have a number of other vessels: the HOS Centerline, with Halliburton pumping equipment; the HOS Strongline; and the BJ Services Blue Dolphin and Halliburton Stim Star IV pumping boats.
A total of 50,000 barrels of mud will be on location to kill the well – far more than necessary, but we want to be prepared for anything. Pumping capacity on location is more than 30,000 hydraulic horsepower.
The mud will be pumped down the 6-5/8 inch drill pipe (pipe is connected to the Q4000), then through 3-inch hoses, which go through the manifold on the seafloor. Then the mud moves through another set of 3-inch hoses attached to the Deepwater Horizon BOP choke and kill lines.
With the manifold, we can also pump the ‘junk shot’ if necessary to stop too much of the kill mud going out through the top of the BOP rather than going down into the well to stop the flow. By switching valves in the subsea manifold, we can inject the ‘bridging material’ (the junk), which will prevent such losses and enable the top kill to continue.

We’ve been testing the junk shot on-shore, looking at different configurations of what might restrict the flow out of the Deepwater Horizon riser and what types of materials would help shut it off. Materials in a junk shot can include well-known items such as pieces of tires, golf balls, and pieces of rope.
Most of the equipment is on site and preparations continue for this operation.

This page was last updated 23 May 2010

http://www.bp.com/genericarticle.do?categoryId=9033657&contentId=7062095

No comments:

Post a Comment

90-Day Plan - 90 Ways to Save Water

Below the Surface - Atchafalaya River Expedition featured in Reader's Digest

Kristian Gustavson receives the American Red Cross "Hero of the Heartland" Award

David Gallo Shows Underwater Astonishments

Below The Surface Podcast

Robert Ballard's TED talk is an inspiring, optimistic look at the future hope of ocean exploration

Water News Network - Live Broadcast Studio

US EPA Water Science News

Be The Solution Shopping Center

Featured Videos

Daily Water News